twitter instagram linkedin linkedin
carbon neutral
curve

News

header example
downarrow

Bioremediation

15 November 2018

Cognition Land & Water Limited was contracted by Enfield Council to bioremediate previously stockpiled grossly contaminated material

Cognition Land & Water Limited was contracted by Enfield Council to bioremediate previously stockpiled grossly contaminated material recovered from excavations during the soil remediation and enabling works at the Willoughby Lane former gasworks site, Enfield using its Advanced Biodegradation Products.

The works included:

Bioremediation trials

The purpose of the trials was to identify the most economically viable and efficient mechanism of reducing contaminant concentrations and improving the visual and olfactory state of the material so that may be used on site. Cognition demonstrated that bioremediation using their additives could be successful and provide a cost effective solution for treating the material.

Pre-processing

The material was processed and homogenized to maximise consistency and provide representative samples for the treatment. Oversize material was screened off and the material was processed using an excavator with a riddling bucket and a screener to ensure an even mix of contaminants and type of material.

Biopile formation

Using an ex-situ land farming technique, the contaminated soil was transferred into a bunded cell with an average depth of 1m. A 0.1m sacrificial layer of clean material was placed over the liner underneath the contaminated soil to protect the liner from tears. The stockpile was turned weekly using the soil mixer and dozer to improve aeration and encourage aerobic activity within the soil.

Inoculation

A tractor mounted soil mixer and spreader was used to spread and mix COGNITION’s treatment additives into the contaminated soils treating 0.5m layers at a time. The soil spreader and mixer was used so that the level of product can be applied uniformly and to break up and loosen the soil which improves aeration and encourage aerobic activity.

Sampling

Prior to trials commencing, baseline samples were taken from the biopiles to confirm the levels of contaminants of concern, as included in the bulk fill validation suite, before treatment and then fortnightly to allow accurate degradation curves to be plotted. 

Monitoring

The biopile was monitored daily during the working week for temperature.  A landfill gas analyser was used to monitor for carbon dioxide, oxygen and methane to assess the level of aerobic microbial activity within each biopile.   

Environmental management plan

An EMP was prepared for the effective management of environmental issues associated with the bioremediation works including:

  • Daily environmental boundary monitoring for odour, VOCs and dust;
  • Continuous boundary monitoring for organic vapours;
  • Downwind dust and odour control systems;

Results

The Bioremediated soil passed the visual and olfactory assessment with all verification samples easily passing the chemical criteria consistently over the biopile. All the soil was re-used and backfilled on the site.

The cleared ground was visually inspected by COGNITION. The visual and chemical assessment found that no material underlying the bio-treatment area had been impacted.

b11.jpg b2.jpg Adding the bioremediation additives b1.jpg Soil mixing b3.jpg
small transparent gif for site construction purposes