Cognition have undertaken a diverse variety of marine works ranging from bathymetric surveys and dredging to demolition and marine installations. We recently completed the decommissioning of a 45m...
MORE >>
Cognition have undertaken a diverse variety of marine works ranging from bathymetric surveys and dredging to demolition and marine installations. We recently completed the decommissioning of a 45m deep pipeline spanning across the river Thames.
Cognition carries out a number of road construction projects per year as part of our civil engineering capabilities or alongside remediation works. We have completed projects such as road...
MORE >>
Cognition carries out a number of road construction projects per year as part of our civil engineering capabilities or alongside remediation works. We have completed projects such as road schemes for Balfour Beatty in Guildford including deep drainage, curbing, beany blocks, ground improvements to an old landfill, tarmac white lining and street lighting and furniture. Another interesting roadworks project completed recently was relocating a coach park for the O2 in Greenwich which included all of the aspects of the Guildford project with additional diversion of services and concrete retaining walls.
Where possible we look at redesigning as much of the schemes to make them more sustainable.
Cognition employs its own drainage gangs and carries out a large number of drainage schemes per year alongside enabling, civil and remediation works. Some of the schemes undertaken include pipe...
MORE >>
Cognition employs its own drainage gangs and carries out a large number of drainage schemes per year alongside enabling, civil and remediation works. Some of the schemes undertaken include pipe jacking under a duel carriageway, deep drainage within confined spaces and new build infrastructure.
Cognition carry out a wide variety of concrete works from capping beams, foundations, lift shafts, concrete frames and tunnel shafts. We recently completed a 21-metre-deep tunnel shaft as part of...
MORE >>
Cognition carry out a wide variety of concrete works from capping beams, foundations, lift shafts, concrete frames and tunnel shafts. We recently completed a 21-metre-deep tunnel shaft as part of the largest bore tunnel in Europe. This involved 24-hour shift working over 7 months. Though some of our works are of typical construction we enjoy working on more complex and difficult structures that many contractors would shy away from. We have a highly motivated, experienced workforce combined with strong technical support from the management team who have years of experience in this field.
Cognition carries out stabilisation to improve and or enhance the geotechnical characteristics and properties of site won materials. The process often involves carrying out trials to select an...
MORE >>
Cognition carries out stabilisation to improve and or enhance the geotechnical characteristics and properties of site won materials. The process often involves carrying out trials to select an appropriate binder such as cement or lime and optimising the binder concentration to achieve the required strength. Cognition pioneered the application of stabilisation for installation of piling mats to reduce import of aggregate. We also use this process to improve subgrade or replace subbase for roads and hard standings. Stabilisation enables the re-use of significant volumes of site soil materials that might otherwise be disposed off-site to landfill. The stabilised materials have increased strength compared to traditional granular fills and stabilised subbase can negate the need for subbase drainage. An additional advantage of stabilisation is that it can encapsulate soil bound contaminants making them less able to leach into groundwater.
Cognition can carry out stability assessments as well as design and install geotechnical solutions to improve slope stability including stabilisation and reinforcement, vegetative walls and gabion...
MORE >>
Cognition can carry out stability assessments as well as design and install geotechnical solutions to improve slope stability including stabilisation and reinforcement, vegetative walls and gabion baskets.
Cognition has designed and delivered a number of site improvement schemes by preloading and surcharging soil prior to development. This type of solution is beneficial where a site is poorly...
MORE >>
Cognition has designed and delivered a number of site improvement schemes by preloading and surcharging soil prior to development. This type of solution is beneficial where a site is poorly compacted or at risk of differential settlement due to varied soil materials within made ground. These schemes often benefit from the installation of vertical band drains and drainage blankets to relieve ground pressure across a site which occurs during surcharging to aid soil consolidation.
Cognition uses state of the art dynamic compacting rollers which are capable of compacting soils to depths of 4-5m. These techniques offer rapid solutions for construction sites. As well as being...
MORE >>
Cognition uses state of the art dynamic compacting rollers which are capable of compacting soils to depths of 4-5m. These techniques offer rapid solutions for construction sites. As well as being able to focus compactive effort at different depths, the roller can identify soft spots and record soil density across the soil profile. Dynamic compaction can be advantageous where progrmame or logistics prevent a traditional excavation and backfill methodology.
Cognition carry out a large number of earthworks projects involving heavy plant for cut and fill operations. We move approximately 2 million cubic metres per year. As part of these works there is...
MORE >>
Cognition carry out a large number of earthworks projects involving heavy plant for cut and fill operations. We move approximately 2 million cubic metres per year. As part of these works there is often a huge volume of geotechnical testing, carried out to demonstrate the fill is done correctly and will not pose a risk for long term settlement.
For many years, due to its adverse impact on resources, carbon emissions, the environment and sustainability, material excavation and disposal (“Dig and Dump”) is considered an outdated practice and last resort. Limited landfill capacity, increasing landfill tax, new and emerging remediation technologies, public perception, and an unwillingness to simply move contamination from one place to another are further reasons why the construction industry is rapidly moving away from this out-dated approach to soil management.
At Cognition Land and Water, our aim is to recycle 95% of all excavated materials to minimise waste generation and disposal, adopt a more sustainable approach, and comply with our net zero carbon commitments. An example of this in practice is the work undertaken at Klondyke on the Isle of Sheppey. Here, we excavated, processed, and treated contaminated soils, only removing untreatable deleterious waste to landfill. We also imported clean, naturally occurring soils from other local sites with a surplus to raise the development platform out of the flood plain, thereby diverting these soils from landfill. All of this work was done under a combined Deposit for Recover Environmental Permit and DoWCoP Materials Management Plan.
This 6.1 hectare site is located at the east side of the Royal Borough of Greenwich on the eastern extremities of Woolwich Town Centre in Plumstead. The proposed development masterplan is for the creation of residential led development, called...
Read MoreCognition Land and Water was commissioned by St William Homes to undertake contamination remediation, ground obstruction removal, materials management, earthworks, pile mat construction and associated groundworks to support the proposed...
Read More The Silvertown Tunnel scheme (STT), when completed, will link North East and South West London from the North Greenwich area to the Royal Victoria Doc area (Silvertown) and will serve to reduce the current congestion at the Blackwall Tunnel.
The site is located at the disused Barking Power Station where City of London Corporation is assembling land for the relocation and amalgamations of the three London Markets. The scope of works comprises the decommissioning of two...
Read MoreThe works involved the decommissioning of the Barking Power Limited (BPL) 610mm (24’’) nominal diameter natural gas pipeline running from BPL’s Above Ground Installation (AGI) at Hordon in the east and to the AGI within the...
Read MoreThe former industrial site was remediated so that it could be further developed for mixed commercial and residential development. Cannon Wharf had a long history of industrial development since 1834, leaving the site contaminated with heavy tar...
Read MoreThe 1.5 hectare site was previously occupied by railway sidings and was redeveloped with the construction of eight student accommodation blocks each between six and eight storeys. The buildings were to be constructed using piled foundation but...
Read MoreNewbury Gasworks site, within the Sterling Industrial Estate, had a long history of industrial use leaving a heavily contaminated site within a built up area of Newbury surrounded by residential and commercial properties. Cognition Land and...
Read MoreThe construction of the rotation chamber for the Silvertown Tunnel and the consequential diversion of Millennium Way will result in the loss of car parking space for the O2 Arena. This will be replaced by the construction of a...
Read MoreThe purpose of the works carried out by Cognition was to facilitate regeneration of the area and the residential led development. We completed additional ground investigation and finalised the remediation strategy and detailed...
Read MoreDealing with one of the largest mixed residential and commercial use building developments in the UK, Cognition had to ensure that their remediation strategy was both cost-effective and sustainable. Extensive Site Investigations identified...
Read MoreThe site was located on the periphery of an industrial estate and encompassed former sludge lagoons used by Guildford sewage treatment works. Gravel abstraction had been carried out on the site since the 1960s and was subsequently used as a...
Read MoreCognition Land and Water was contracted by FM Conway Limited to undertake remediation and earthworks for the redevelopment of the former Southall Gasworks. The site was surrounded by watercourses with a central tip area containing...
Read More